Buyer's Guide

OEM Power-Supply Enclosure RFQ: Defining the Mechanical Package

Prepare an OEM power-supply enclosure RFQ with controlled inlet, PCB, fan and mounting interfaces, plus clear mechanical supply and inspection scope.

DRAmetal Engineering Team October 15, 2026 5 min read
OEM Power-Supply Enclosure RFQ: Defining the Mechanical Package

A custom power-supply enclosure is purchased as part of an electrical assembly, but its fabrication package should clearly identify the mechanical work being ordered. The metal shell, mounting hardware, insulating components, inlet and fan may come from different suppliers. Leaving those boundaries implicit makes pricing unreliable and increases assembly risk.

The best RFQ brings the mechanical interfaces together without asking the metal fabricator to infer electrical safety requirements. The responsible equipment designer supplies the approved electrical constraints; the fabrication drawing translates them into inspectable physical features.

List the supplied and customer-supplied components

Identify the base, cover, partitions, brackets, standoffs and inserted hardware. State whether the enclosure arrives assembled or as a kit. List the inlet, connectors, fan, board and insulating pieces separately, even when they are provided only as samples for first-article fitting.

Define responsibility for selecting those components and approving substitutions. Two inlet bodies with the same electrical designation may use different mounting arrangements. A quotation should not silently replace a customer-selected part with another item merely because its front opening appears similar.

Treat the inlet and its panel geometry as one controlled interface.
Treat the inlet and its panel geometry as one controlled interface.

Release a common mechanical interface package

Provide the enclosure drawing, model and current mating-component information. Establish the assembly datums before dimensioning the inlet, fan pattern and board supports independently. A shared reference helps inspection evaluate how those features relate after bending and hardware insertion.

Include installed and service envelopes. The PCB may fit in the base while a rear connector, cable or cover screw interferes during assembly. Show the intended order of installation and the spaces reserved by the equipment designer. Mark unresolved interfaces rather than converting a provisional model into an approved manufacturing requirement.

PackageInput neededResponsible boundary
Shell and coverMaterial, datums, formed geometry and finishDrawing-led fabrication
Inlet / connectorsExact model, mounting and mating envelopeSelected by equipment owner
PCB supportsHole pattern, height and protected zonesApproved mechanical / electrical design
Insulators / bondingSpecified parts and controlled interfacesElectrical design authority
AcceptanceSamples, assembly state and required reportsAgreed mechanical and system tasks

Keep electrical decisions with the responsible designer

Provide the released requirements for insulation, protective bonding, accessible edges and any protected zones. Do not substitute a generic clearance value based on enclosure size. Electrical spacing and qualification depend on the complete design and the applicable assessment.

The metalwork supplier can fabricate and inspect specified features, provide agreed records and participate in interface review. That is different from supplying a certified complete power supply. Keep mechanical first-article acceptance separate from the equipment’s electrical, EMC and thermal qualification activities.

Board supports need a shared assembly datum.
Board supports need a shared assembly datum.

Specify the finished assembly condition

Identify the material, thickness, coating system and hardware installation sequence. Where finish affects a mating surface, hole or inserted component, state the acceptance condition after finishing. Cosmetic requirements should not obscure a functional dimension.

Include markings and identification in the controlled scope. If panel labels are required, the approved artwork must match the current connector arrangement. An old label revision can turn a mechanically correct enclosure into an incorrectly identified assembly, so review the artwork and mechanical drawing together.

Use the first article to close interface questions

Agree which customer components will be used for trial fitting and how many enclosure samples are checked. Record inlet seating, board support, fan alignment, cover closure and fastener access as separate observations. Do not extend three successful complete assemblies into a claim that every unit in a larger batch received the same trial.

DRAmetal’s linked project retained separate sample quantities for inlet and dimensional checks and complete mechanical assembly. That is the useful model for an OEM RFQ: define the evidence needed for each interface, then preserve the distinction in the acceptance record and repeat-order plan.

A fabrication package should name every supplied metal component.
A fabrication package should name every supplied metal component.

DRAmetal supplies custom power-supply enclosure metalwork to released OEM requirements. Read the mechanical-fit customer project for its specific inspection scopes, then provide your own drawings, mating components and batch plan for quotation.

Need a Custom Sheet Metal Quote?

Send us your CAD drawings — DRAmetal's initial response target is within 24 working hours. Quotation, DFM and lead-time timing depend on file completeness and engineering scope.

GET A FREE QUOTE →
DRAmetal Engineering Team

Team-authored manufacturing guidance. Scope, sources, corrections, and project-status labels follow our engineering content policy.