A fabricated pass-box cabinet has several acceptance boundaries. The shell must fit the wall, its frames must match the doors, and its interior must meet the specified construction and finish. A single statement that the cabinet was inspected does not explain which of those relationships were checked.
An OEM acceptance plan should identify the supplied assembly and the evidence required for each interface. Keep mechanical delivery checks distinct from the customer’s cleanroom, cleaning or control-system qualification.
Match the inspection scope to the delivery
Start with the bill of materials and the as-delivered state. If the fabricator supplies only the body, liner and hinge seats, list the customer components needed for trial fitting. If doors or shelves are included, add their finished assembly checks.
Record the drawing revision and any approved departures before inspection begins. A report generated against an obsolete door or wall opening can appear complete while checking the wrong interface. The inspection reference must match the configuration that purchasing has released.

Inspect the wall and mounting relationship
Check the body envelope, flange, mounting holes and the surfaces used for positioning. Identify whether the inspection uses dimensional measurement, a fixture or an actual installation. Each provides different information.
Where the customer reports a successful site fit, retain the location reference privately and publish only the authorized anonymous outcome. Do not treat a three-unit installation sample as a full-batch dimensional report. State what was observed and which units or sample quantity it covered.
| Acceptance item | Evidence type | Scope to record |
|---|---|---|
| Body and flange | Dimensions / fixture / installation | Revision and units checked |
| Door relationship | Trial fit and gap measurement | Hardware, state and sample |
| Interior finish | Visual and specified measurements | Surfaces and locations |
| Mounting provisions | Selected hardware trial | Actual supplied configuration |
| Delivery | BOM and packing inspection | Protected parts and records |
Trial the door and service movement
Use the selected doors and hardware where the agreed plan requires them. Inspect closed gaps at defined locations and check the intended opening movement. Include strike alignment, stops and access to any removable component.
The mechanical record should not claim interlock functionality merely because its mounting holes exist. If the customer owns the control hardware and testing, identify that next acceptance activity separately. This avoids turning a successful hinge trial into a statement about the complete equipment’s operating logic.

Inspect liner finish and accessible edges
Review the surfaces identified on the drawing for joint construction, finish and edge condition. If roughness measurements are required, record the method and locations rather than only a single number. Check shelves and support details in the relevant assembled states.
Surface appearance, measured roughness and customer cleaning validation are separate evidence types. The linked project retained a five-unit surface sample and customer feedback, while wall installation used a different sample. Keeping those scopes visible makes the record more credible and easier to reuse.
Close the delivery record and preserve it for repeats
List the supplied components, inspection results, unresolved items and approved configuration. Protect finished surfaces and mating features for shipment. Identify any customer-supplied sample that was used during the trial so later changes can be evaluated against the same reference.
For a repeat order, review whether the wall, door, hardware or finishing requirement has changed. Reuse valid unchanged evidence where appropriate, but repeat checks affected by the revision. A useful acceptance plan supports efficient purchasing because it makes both the delivered work and remaining system tasks clear.

Review pass-through cabinet metalwork with DRAmetal using your cabinet drawings and installation interfaces. The wall-fit and door-alignment customer project reports the specific results and samples behind one completed fabrication program.
Need a Custom Sheet Metal Quote?
Send us your CAD drawings — DRAmetal's initial response target is within 24 working hours. Quotation, DFM and lead-time timing depend on file completeness and engineering scope.
GET A FREE QUOTE →