A robot motion module OEM may source a welded base, machined rail interfaces, sheet metal guards and installation hardware from one mechanical supplier while purchasing the rail, carriage, drive, motor, cable carrier and controls elsewhere. The fabrication RFQ has to define those boundaries precisely. Otherwise, suppliers quote different scopes and the lowest number may omit the inspection or packout needed at integration.
This guide is not a general seventh-axis design tutorial. It focuses on the information required to quote and manufacture released base and guard metalwork, preserve interfaces and deliver useful evidence.
DRAmetal manufactures the released mechanical scope. The robot OEM or integrator owns motion sizing, loads, rail and drive selection, foundation and anchoring design, robot programming, electrical integration, guarding strategy, risk assessment, applicable certification and final machine validation. Qualified safety and electrical personnel must approve the complete system.
Divide the motion module into quotable supply packages
Start with a supply-boundary drawing or table. List every item and identify whether it is supplied by the fabricator, shipped free-issued by the buyer, installed by another contractor or excluded. A visual assembly model alone does not establish commercial responsibility.
A mechanical fabrication package may include:
- Welded base beams, cross-members, feet and splice frames.
- Machining stock or finished rail-mounting pads.
- Leveling, lifting and anchor-interface metalwork.
- Cable-carrier troughs and support brackets.
- Formed sheet guards, removable panels and access covers.
- Drawing-defined inserts, hinges, latches and fasteners.
- Loose installation kits and revision-controlled labels.
Purchased rail components, gear racks, bearings, motors, cables, switches and safety devices should appear in the boundary even when they are excluded. Their envelopes and mounting interfaces still affect the fabricated parts.
For a multi-part module delivered as one mechanical kit, robotic welded OEM assemblies is the relevant transaction page. A long base specifically supporting linear robot travel maps to robot seventh-axis base frames.
Release a single interface control model
The interface control model should contain the geometry needed to connect base sections, rail components, guards, the floor and adjacent cell equipment. Mark the controlling coordinate system and keep it consistent across every part drawing.
Important interfaces typically include:
- Rail-pad faces, pilot features and mounting holes.
- Drive, gearbox, rack or belt support interfaces.
- Base-section splice faces and matched hardware.
- Leveling points, anchor holes and installation access.
- Cable-carrier path, end conditions and moving keep-outs.
- Guard supports, panel gaps and removable service zones.
- Robot travel envelope and adjacent equipment keep-outs.
The OEM should release nominal geometry, tolerances and acceptance criteria based on its system design. The supplier can review fabrication and inspection feasibility, but should not infer allowable rail misalignment or guard clearance from a rendered assembly.
Define the welded base by functional features
A motion-module base is not accepted by overall length and width alone. Long weldments can contain local twist, pad variation and splice mismatch even when the envelope looks correct. The RFQ should identify which features establish installation and rail geometry.
State whether rail pads are welded plate, machined after welding or separate bolted details. If machining is required, include stock, datum pickup and final inspection requirements. Define whether modular sections are inspected individually, assembled in a factory setup, or verified through matched interface features and an installation procedure.
The weld specification should include symbols, joint preparation, required workmanship standard or buyer specification, and any required personnel or procedure documentation. Do not ask for “robotic welding” as a quality level. The joining process should be selected and qualified for the actual material, joint, access and acceptance requirements.
Lifting points and transport restraints deserve the same control as operating interfaces. The OEM or responsible engineer must approve their loads and use. Fabrication drawings should state whether lifting features remain on the machine, are removable or are used only under a separate handling instruction.
Treat guards as maintained machine components
Sheet metal guards must fit the released structure, provide required clearances and remain removable for approved service tasks. Their presence alone does not establish machinery safety. The risk assessment and qualified safety design determine required coverage, openings, access control, interlocks and safe distances.
For fabrication, define panel materials, thicknesses, edges, seams, supports, fasteners and finish. Identify doors and panels that are routinely removed, and provide controlled handling features where required. Keep fastener access out of the motion envelope and prevent loose hardware from entering rail or drive areas.
Guard design should account for the as-installed stack: coating, gaskets, edge trim, hinges, latches and mounting hardware can change gaps and alignment. If viewing windows, mesh, sensors or interlock devices are installed by another party, include their released openings and mounting provisions while keeping their performance validation outside the metalwork scope.
Specify inspection by manufacturing state
Some characteristics exist before welding, some after welding, some after machining and others only after trial assembly. The inspection plan should identify the state for each result. A pre-weld hole coordinate does not prove the final rail-pad relationship.
Use characteristic IDs that tie drawing requirements to the FAI report. For long bases, agree how the part is supported and whether it is measured free, leveled, restrained or assembled with neighboring modules. Record the fixture or support condition so the data can be reproduced.
The acceptance table below can be adapted to the released package:
| Deliverable | Typical controlled characteristics | Evidence to request | System boundary |
|---|---|---|---|
| Welded base section | Datum targets, pad locations, splice interfaces and anchor features | Ballooned dimensional report and fixture/support record | Does not validate rail performance |
| Machined rail pads | Final face relation, hole pattern and surface requirement | Final-state measurement report | Rail alignment criteria come from OEM |
| Modular joint | Match identification, interface location and hardware | Trial-fit or approved interface evidence | Field installation remains controlled work |
| Sheet metal guards | Panel fit, gaps, edges, hardware and finish | Assembly check and cosmetic record as specified | Does not certify machine guarding |
| Mechanical kit | Part count, revision, labeling and protected packout | BOM reconciliation and packing record | Electronics and safety devices excluded unless contracted |
Inspection frequency after first article should come from the approved quality plan. Avoid imposing “complete inspection” without identifying characteristics, methods, records and commercial scope.
The downloadable robotics frame FAI and datum checklist provides a practical structure for datum, characteristic, equipment and deviation planning.
Make variants and revisions visible
Motion modules often share a common base while changing travel length, rail model, motor side, cable-carrier route or guard layout. The RFQ should separate true common parts from variant-specific parts. A family table is more reliable than filenames that differ by one suffix.
Include the effective revision of the interface control model, BOM, part drawings, weld documents, finish specification, inspection plan and packout instruction. If buyer-supplied components are used for trial fit, identify their revision and disposition after inspection.
Define the change process before production. The supplier should not relocate holes, split panels or substitute hardware based only on shop convenience. Proposed DFM changes require documented OEM review, updated releases and any revalidation required by the responsible teams.
The existing robot seventh-axis base-frame fabrication guide explains broader rail-datum and modular-base principles. Keep this RFQ article focused on scope comparison, evidence and delivery so the two pages do not compete for the same intent.
Quote packout, transport and site handoff
Long bases and large guard panels can leave the factory conforming and arrive difficult to identify or assemble if packout is undefined. Include module size and transport constraints in the RFQ, then agree where the fabricator’s responsibility ends.
Useful delivery requirements may cover:
- Section and match-mark identification tied to the installation drawing.
- Protected rail pads, machined faces and finished panel surfaces.
- Separate hardware kits by module, joint or assembly step.
- Temporary braces or shipping frames released by the responsible engineer.
- Lifting-point labels and handling documentation supplied by the OEM.
- Packing lists that identify part number, quantity and revision.
- Required inspection reports and approved deviation records.
- Destination, transport mode and buyer-defined packaging constraints.
Do not assume the fabrication supplier commissions the module because it ships an assembled base. Rail installation, alignment, electrical work, guarding completion and machine validation remain with the parties identified in the contract and safety plan.
Related customer project: Robot Seventh-Axis Base: Post-Weld Rail Alignment.
Issue a comparable OEM RFQ checklist
Use one controlled checklist so each bidder prices the same mechanical boundary:
- Assembly model, interface control model and part drawings share one released revision.
- Supplier, buyer-free-issued, integrator-installed and excluded items are identified.
- Rail, drive, carrier, foundation and guard interfaces have released requirements.
- Weld symbols, material, machining stock and finish are defined.
- Datum sequence and support or restraint condition are stated.
- FAI characteristics, variable data and report format are listed.
- Guard panels, doors, hardware and service-removal requirements are complete.
- Trial assembly and buyer-supplied component responsibilities are stated.
- Variants, quantities and change-control rules are included.
- Packout, transport, destination and site-handoff boundaries are defined.
- OEM/integrator ownership of motion design, electrical work, safety, certification and final validation is explicit.
Use the robotics manufacturing hub to connect this motion-module package with related robot structures and mechanical kits. Once the released drawings, interface model, evidence plan and delivery boundary are complete, send the OEM RFQ for project-specific fabrication review and quotation.
Need a Custom Sheet Metal Quote?
Send us your CAD drawings — DRAmetal's initial response target is within 24 working hours. Quotation, DFM and lead-time timing depend on file completeness and engineering scope.
GET A FREE QUOTE →