A pre-terminated harness may not pass through an ordinary gland-plate hole because its connector is larger than the cable. A split plate can create an assembly path around the harness, but cutting a plate into two pieces does not by itself create an approved split cable-entry system.
An OEM RFQ needs to distinguish the metal support from the selected cable-entry components. The plate joint, support, fasteners and sealing arrangement must work with those components and with the cabinet’s assembly sequence.
Define which component actually surrounds the cable
Identify whether the design uses a proprietary split entry frame, split gland or another engineer-approved cable-entry arrangement. The metal plate may simply support that component. Do not split an ordinary one-piece gland or its mounting hole and assume it retains its original function.
Provide the entry-system installation drawing and the largest connector envelope that must pass through during assembly. Include any strain-relief or shielding accessories specified by the equipment designer. This establishes what opening the metalwork must provide and which interfaces remain controlled by the entry-system supplier.

Locate the plate joint around the assembly task
Show how the harness enters before the plate sections are brought together. Decide which section remains fixed and which must move, including the access needed to insert and tighten its fasteners. A joint line that looks convenient in the flat pattern may be inaccessible inside the cabinet.
Review support near the joint and the opening. The sections need a defined relationship when assembled; an uncontrolled edge-to-edge gap cannot be treated as a repeatable reference. Use the released locating and fastening features rather than relying on the installer to align the halves by sight.
| Interface | Release information | Acceptance owner |
|---|---|---|
| Harness passage | Connector envelope and entry sequence | OEM assembly team |
| Split entry component | Selected system and instructions | System supplier / OEM |
| Metal sections | Location, support and fastening | Fabricator |
| Sealing joint | Approved detail and validation condition | Equipment validation team |
| Bonding provisions | Contact design and required test | OEM electrical team |
Agree the sealing and bonding interfaces explicitly
If environmental sealing is required, the equipment designer should define the joint arrangement and validation plan with the selected entry components. A gasket under the perimeter of the plate does not automatically resolve a split through the plate itself.
Likewise, electrical continuity and shielding are separate design and acceptance tasks. Fastening two coated sections together is not sufficient evidence of a particular bonding resistance or shielding performance. Specify any required contact provisions and keep their inspection separate from ordinary dimensional acceptance.

Check the harness handling and reassembly sequence
Review the installation using a representative pre-terminated harness or a controlled envelope. Confirm that the connector can pass without being forced against cut edges, and that the plate can close without trapping the cable or loading the termination.
Repeat the planned service sequence where removal is part of the requirement. The relevant question is whether the entry system and plate can be reopened and restored using the approved procedure, not whether the initial assembly can be completed once before the rest of the cabinet is populated.
Write acceptance around the released split assembly
Inspect both sections as parts and then as an assembly. Record their location, joint relationship, hardware fit and interface to the chosen entry system. Identify which checks belong to the fabricator and which are completed by the cabinet builder after cable installation.
Do not transfer the linked conventional gland-plate project’s measured results to a split design. It is a useful example of documenting hardware and sampling, but a different joint and entry system need their own acceptance. Clear scope prevents an attractive fabrication concept from being mistaken for a validated enclosure configuration.

Review custom cable gland plates with DRAmetal using your gland BOM, hole map and assembly acceptance requirements. The gland-plate customer project shows how array measurements, actual fitting trials and grounding-stud checks were recorded separately.
Need a Custom Sheet Metal Quote?
Send us your CAD drawings — DRAmetal's initial response target is within 24 working hours. Quotation, DFM and lead-time timing depend on file completeness and engineering scope.