The project combined containment roofs, end doors and opening roof panels for an energy-efficiency retrofit.
The customer’s challenge
The containment roof did not release reliably during fire-system activation or abnormal temperature conditions.
Material and fabrication route
Aluminum profiles and tempered glass; Q235 steel structural frame.
Process route: Profile cutting → sheet metal bending → welding → assembly → site installation and commissioning.
Manufacturing changes
Fusible-alloy and electromagnetic release mechanisms provided two roof-release triggers integrated with the fire system.
Engineering analysis
The containment assembly had both an airflow function and a release interface. The recorded interlock result concerns the installed release arrangement, including its relationship with the fire system. The reported PUE change is a site-level observation after the retrofit; it is not an intrinsic rating of an individual sheet metal roof panel. These two outcomes should remain separate in procurement and acceptance discussions.
Inspection and project results
The installed system passed the reported interlock test. The site also recorded lower PUE after the containment changes; this result applies to the project installation.
| Project measurement or production detail | Recorded value |
|---|---|
| Roof-release response | ≤5 seconds |
| Recorded PUE reduction | 0.1–0.2 |
| Aisle width | 1,200 mm |
| Rack height | 42U |
These figures describe the project configuration and production scope above. Dimensional, material and production details are identified separately from performance tests. For a new order, the inspection method and acceptance criteria should be agreed against the released drawings.
Planning a similar OEM component
A useful RFQ for this application should make the following interfaces and acceptance requirements clear:
- Aisle and rack dimensions.
- Roof-release and interlock interfaces.
- Installation and commissioning scope.
- Site-level energy comparison basis.
Include the current drawing revision, mating-component information, quantities and required delivery sequence. Identifying unresolved requirements at quotation stage helps distinguish fabrication work from the equipment-level checks that the project needs.
For related manufacturing support, review our Aisle Containment and sheet metal quality capabilities. Use the existing quotation form below to share the drawing package for review.