A dust collector housing has several interfaces that must work together: filter mounting, duct flanges, the service door and the hopper outlet. This project delivered six housing sets for a four-cartridge collector design. The scope covered the fabricated metalwork and mechanical interfaces, with actual measurements for fit, a defined vacuum-hold check and wall deflection under the project’s negative-pressure condition.
The records also identify rework. A hopper-outlet hole pattern differed from the selected unloading valve, one unit needed internal spatter removal, and the door-latch effort remained a possible maintenance improvement. Publishing those details makes the manufacturing sequence clearer than reporting only a general acceptance statement.
The supplied housing package
The upper body used 2.0 mm SPCC steel, the hopper 2.5 mm, the access door 1.5 mm, and the top connection flanges and reinforcing features 3.0 mm. Internal and external surfaces received RAL 7035 powder coating, with primer at weld areas. Internal contact surfaces were dressed to remove protruding weld residue.
The delivery contained six upper housings, six hoppers and six side access doors, with inlet and outlet flanges, filter mounting plates and grounding terminals. Each housing was arranged for four cartridge positions. That configuration does not establish a filter efficiency or airflow rate without the selected filters and complete equipment validation.
The specified hopper geometry included a 60° angle. The case retains that project geometry without inferring a discharge rate or a guarantee against material bridging. For comparable packages, the housing RFQ and filter-interface guide identifies the component drawings needed before the metalwork can be quoted as a complete assembly.
Flange and cartridge-interface measurements
The first article received full-dimensional inspection and assembly checks. Two production units received repeated flange, sealing and deflection checks. Remaining-unit coverage is described separately below rather than treating the entire batch as quantitatively tested.
Recorded housing-envelope deviation was within ±1.0 mm. Inlet and outlet connection-flange flatness was ≤0.15 mm, and the checked mating interfaces showed no visible open gaps. Filter mounting-hole position was ≤0.2 mm, with smooth cartridge mounting in the checked assembly. These results describe the mechanical fit of the selected interfaces, not interchangeability with every cartridge format.
The tube-sheet hole-pattern guide explains why the filter’s selected retention and seating details matter alongside hole centres. The manufacturing drawing must preserve the actual cartridge interface rather than using only an outside diameter as a substitute for the full mounting definition.
A defined, isolated-source vacuum-hold check
The owner confirmed the fixture arrangement and sign convention. The inlet and outlet connections, hopper discharge and filter openings were blanked, and the access door was closed and latched. The housing was evacuated to −1500 Pa gauge, then the valve was closed to isolate the vacuum source before timing. The acceptance limit was a pressure rise toward ambient of no more than 30 Pa in 30 seconds.
For clarity, a limiting change from −1500 Pa toward −1470 Pa is a 30 Pa rise; it is not a further increase in vacuum magnitude. The reported checked units met the project’s limit. The record does not convert this short-duration pressure result into a volumetric leak rate, which would require additional information about the setup and conditions.
The first article and two additional production units completed the quantitative timed check: three of the six housings. The remaining three did not receive the timed quantitative test; they received visual weld, gasket-contact and light-gap checks. This coverage is an important part of the result and is not reduced to an unqualified “all housings passed pressure testing” statement.
This was the project’s factory/field acceptance method, not a third-party type test. It does not establish an explosion-pressure rating, emissions performance or filter-media efficiency. Any new pressure-test setup requires its own controlled procedure and safety review; the values here are project records, not instructions to pressurize another housing.
Wall movement at the same operating condition
Wall deflection was checked with a dial indicator at the sidewall’s geometric centre. At the stabilized −1500 Pa gauge condition, the maximum reported inward deflection was 0.8 mm, meeting the project’s ≤1.0 mm internal criterion. The first article and two production samples received this check.
After pressure release, the recorded residual displacement was ≤0.1 mm. This measured bound is retained instead of replacing it with an absolute “zero residual movement” claim. The results apply to the checked wall configuration and pressure condition, not to deeper vacuum, positive pressure or different panel spans.
The housing inspection-fixture guide covers how to identify support conditions, sealing boundaries and measurement locations so that repeated checks refer to the same physical setup.
Finish, grounding and completed corrections
Measured exterior coating thickness was 70–90 μm, with 60–80 μm internally. The inspected welds were visually continuous and the finished areas were dressed. Visual continuity is not described as a nondestructive-test result. The owner also reported terminal continuity ≤10 mΩ; this is not expanded into certification of the complete installation’s grounding system.
The first hopper outlet showed a 2 mm hole-pattern mismatch against the selected standard unloading valve. The flange-hole tooling was corrected, and all six delivered housings had the affected holes enlarged on site and accepted. The case does not invent a new hole diameter or claim that later, unreworked production has already been verified.
One housing retained a small amount of internal welding spatter. It was dressed and cleaned, with an additional internal cleaning step requested for production. The access-door latches required more opening effort than preferred. An assist handle was identified as an option but was not fitted; the higher-effort operating condition remains visible in the record.
Acceptance coverage and the next manufacturing release
| Item | Recorded result | Coverage or limitation |
|---|---|---|
| Connection geometry | Flange flatness ≤0.15 mm; filter-hole position ≤0.2 mm | Project interface measurements, not universal cartridge compatibility |
| Vacuum hold | −1500 Pa gauge; source isolated; rise ≤30 Pa in 30 s | First article plus two production units; three remaining units not quantitatively tested |
| Sidewall movement | Maximum 0.8 mm at −1500 Pa; residual ≤0.1 mm | Same three-unit test scope, sidewall-centre measurement |
| Outlet interface | 2 mm pattern mismatch corrected on all six units | Tooling updated and delivered holes reworked |
| Internal finish | One spatter area dressed and cleaned | Additional internal cleaning step requested |
| Service access | Door closes and seals; opening effort remains higher than preferred | Optional assist handle not installed |
For custom dust collector housings, the repeat-order priorities are the corrected valve interface, selected cartridge geometry, defined seal boundaries and the actual inspection coverage. The service-door improvement should be reviewed with the customer rather than silently treated as completed. These controls connect a useful fabrication record to a clearer RFQ while preserving the boundary between housing manufacture and complete dust-collection-system performance.