A medical equipment customer needed precision stainless sheet-metal parts that met a defined surface condition and could be traced by batch. The component family included mounting plates, brackets and fluid-line support plates. Their acceptance depended on both the fabricated features and the surface remaining after forming and finishing.
The project coordinated cutting, bending protection, electropolishing and citric passivation, then connected surface inspection to batch records. Recorded roughness values were Ra 0.25–0.38 μm, within the specified Ra ≤0.4 μm requirement. All sampled free-iron test locations passed, appearance inspection passed, and the customer accepted the parts and added the supplier to its approved supplier list.
Why the previous route did not meet acceptance
The customer required no free-iron indication under the specified test and a controlled roughness limit on the outside bend surfaces. Under the previous supplier’s conventional passivation route, sampling had found unacceptable free-iron indications around bend marks. Roughness also varied between batches.
Those problems prevented acceptance by the customer’s medical quality department. A process label alone was therefore not enough: the revised route needed to address the actual areas that failed inspection and provide consistent records for subsequent batches.
The project did not treat a smoother appearance as a substitute for surface verification. Roughness, free-iron testing and visual acceptance remained separate checks, each with its own recorded coverage.
Material and manufacturing route
The parts used 304 stainless steel sheet, 1.0–1.5 mm thick, with 2B/BA starting surfaces. The formed component family included flat mounting regions, bends, cut edges and attachment features for installation inside medical equipment.
Recorded route: Nitrogen-assisted laser cutting → deburring → bending → electropolishing → citric passivation → ferricyanide free-iron testing → dust-controlled packaging → batch traceability.
The work combined fabrication and finishing controls. Cutting and bending established the surface condition entering the finishing sequence; the later inspections evaluated the agreed finished condition. Packaging and traceability then carried that accepted condition into the shipment process.
What changed in the manufacturing approach
The laser-cutting route used nitrogen assistance to reduce oxidation at the cut. Bending used polyurethane tooling protection to address the marking problem associated with the previous process. These changes addressed upstream contributors rather than leaving the entire correction to the final passivation operation.
Electropolishing preceded citric passivation in the revised finishing route. Citric treatment replaced the previous nitric route for this project. The process choice belonged to the accepted component configuration; it was not presented as a universal replacement for every stainless alloy or customer specification.
The inspection plan added per-batch free-iron checks and roughness measurement. Batch traceability cards linked the manufactured parts to their processing and inspection history. Together, the changes gave the customer a clearer relationship between the ordered components, the finishing route and the acceptance records.
Inspection results and sampling coverage
| Inspection item | Project requirement | Recorded result | Recorded coverage |
|---|---|---|---|
| Outside-bend roughness | Ra ≤0.4 μm | Ra 0.25–0.38 μm | Five points per piece, three pieces per batch |
| Free-iron verification | No blue indication under the specified ferricyanide test | No blue indication at all sampled locations; accepted | Three pieces per batch, three test locations per piece |
| Appearance and edge condition | No scratches, oxidation color or burrs | Visual and 10× magnification inspection passed | 100% appearance inspection |
The free-iron result means all tested locations in the recorded sample passed. It does not mean every delivered piece underwent that chemical test. Appearance inspection, by contrast, was recorded as 100% coverage. Keeping those scopes separate makes the project result useful without overstating the inspection population.
The roughness range is the recorded result for this project, not a tolerance offered automatically for every DRAmetal component. A new part still needs its own surface regions, measurement conditions and accepted manufacturing route.
Customer acceptance and supplier approval
The project achieved complete batch traceability and passed the customer’s medical quality review. The supplier was added to that customer’s approved supplier list. This is a customer procurement and quality outcome for the component program, not an additional device certification or a claim that all future part configurations share the same approval.
The useful outcome was broader than a single passing sample. The manufacturing route, inspection coverage and traceability records were brought into a form the customer could accept for the supplied part family.
Engineering lessons for a comparable OEM program
The project illustrates why surface problems should be reviewed across the route. A finishing operation cannot be evaluated in isolation from the condition created by cutting, forming and handling. The observed problem at bend-marked regions made both upstream protection and final location-specific inspection important.
The results also show why acceptance records should name their coverage. A roughness range, a sampled qualitative test and a full visual inspection describe different aspects of the same shipment. They become more useful when their locations and sample counts are retained instead of condensed into a generic “passed inspection” statement.
For a comparable program, passivated stainless steel parts should be quoted against released drawings, surface zones and the customer’s required records. The guides to roughness measurement near bends and ferroxyl test reports provide practical questions for defining that scope before production.