Agricultural & Heavy Equipment

Mining Control Cabinet: Door Seals and Ready-to-Fit Holes

The cabinet protected low-voltage controls and variable-frequency-drive components used around mining equipment.

Anonymous Customer Case Study

📅 October 7, 2025 ⏱ 3 min read 🏭 DRAmetal Engineering
Mining Control Cabinet: Door Seals and Ready-to-Fit Holes — component reference
Component reference image
IP65 Protection test
800 × 600 × 2,000 mm Cabinet size
60–80 μm Powder-coat thickness
±0.1 mm Hole-position tolerance

Project Overview

Application The cabinet protected low-voltage controls and variable-frequency-drive components used around mining equipment.
Materials Q235B cold-rolled steel; galvanized mounting beams; 304 stainless option for specified humid or corrosive environments.
Process Route Laser cutting → CNC bending → tack and structural welding → edge and weld dressing → cleaning and phosphating → outdoor powder coating → hardware and seal assembly → protection inspection.
Customer Challenge Dust and moisture entered through door gaps and caused contamination. Thin coating at poorly dressed corners corroded, while mismatched mounting holes required drilling on site.

The cabinet protected low-voltage controls and variable-frequency-drive components used around mining equipment.

The customer’s challenge

Dust and moisture entered through door gaps and caused contamination. Thin coating at poorly dressed corners corroded, while mismatched mounting holes required drilling on site.

Material and fabrication route

Q235B cold-rolled steel; galvanized mounting beams; 304 stainless option for specified humid or corrosive environments.

Process route: Laser cutting → CNC bending → tack and structural welding → edge and weld dressing → cleaning and phosphating → outdoor powder coating → hardware and seal assembly → protection inspection.

Manufacturing changes

Revised door returns and aging-resistant seals improved protection. Rounded edges and adjusted coating parameters covered vulnerable corners. Customer component dimensions were confirmed before laser-cutting the mounting pattern.

Engineering analysis

The cabinet had three installation problems: ingress at the door, corrosion at vulnerable edges, and holes that did not match the equipment. Seals, edge preparation and confirmed mounting dimensions addressed those problems directly. The coating and hole-position results support the reported ready-to-fit installation. This case concerns the stated cabinet configuration and does not add an unreported explosion-protection qualification to the metal enclosure.

Inspection and project results

The cabinet met the project’s dusty, humid operating requirement, resolved the observed edge corrosion and allowed direct installation without secondary drilling.

Project measurement or production detailRecorded value
Protection testIP65
Cabinet size800 × 600 × 2,000 mm
Powder-coat thickness60–80 μm
Hole-position tolerance±0.1 mm
Production quantity50 cabinets/month

These figures describe the project configuration and production scope above. Dimensional, material and production details are identified separately from performance tests. For a new order, the inspection method and acceptance criteria should be agreed against the released drawings.

Planning a similar OEM component

A useful RFQ for this application should make the following interfaces and acceptance requirements clear:

  • Component mounting dimensions.
  • Door returns and seal interfaces.
  • Edge preparation and coating specification.
  • Dust, moisture and installation acceptance.

Include the current drawing revision, mating-component information, quantities and required delivery sequence. Identifying unresolved requirements at quotation stage helps distinguish fabrication work from the equipment-level checks that the project needs.

For related manufacturing support, review our Industrial Control Cabinet and sheet metal quality capabilities. Use the existing quotation form below to share the drawing package for review.

More Manufacturing Projects