A motor terminal box can fit its overall envelope yet still create problems at the motor seat, cable glands or grounding connection. This project supplied 36 fabricated box-and-lid sets for an OEM motor application. The work combined a controlled mounting interface with three cable entries per box and a lid that could be removed by hand after the equipment was safely isolated.
The project record includes dimensional and installed-fit checks, a separately sampled field sealing check, and two practical assembly corrections. It also retains a grounding-position issue for further design review. These details are useful to buyers specifying a repeatable terminal-box package rather than purchasing an empty enclosure by external dimensions alone.
The delivered metalwork and hardware package
The housings used SPCC cold-rolled steel, divided into a 1.5 mm body, 1.2 mm lid and 2.0 mm bottom mounting plate. Laser-cut edges were deburred and rounded to the specified R0.3 condition. The finish was RAL 7035 electrostatic powder coating; tapped internal threads received the specified anti-rust treatment after tapping.
The delivery included 108 preinstalled PG13.5 cable glands, three per box, and 36 spare-opening plugs, together with M4 grounding screws, sealing strips and the required fastening hardware. The counts identify the delivered components; they do not imply that every accessory underwent every test described below.
The terminal-board mounting positions aligned in the checked assemblies, with sufficient room for the intended wiring operation. For a repeat package, the board footprint and cable approach should remain part of the controlled interface definition. Our terminal-box RFQ guide separates those requirements from the motor-frame mounting pattern.
First-article measurement and production fit samples
One first-article set received full-dimensional CMM inspection. Six production sets received key-dimensional checks and trial assembly on the motor interface. The latter is a six-set sample from a 36-set delivery, not full-dimensional inspection of every delivered box.
Recorded external dimensional deviations were within ±0.5 mm. The position tolerance recorded for the four 6.5 mm mounting holes was ≤0.12 mm, while the motor-seat mating face had recorded flatness ≤0.08 mm. The checked trial assemblies fitted without warping after fastening. The reported complete fit applies to those checked assemblies, rather than an invented 100% dimensional inspection of the shipment.
The flange and the box skin serve different functions. A small error at a seating land can affect how the gasket and motor interface come together even when the enclosure envelope is acceptable. The finished flange and gasket-seat guide describes how to keep that functional surface visible in a fabrication drawing and inspection plan.
Cable glands, lid removal and field sealing
The PG13.5 entry threads passed the reported full go/no-go gauge check. A gland-retention check was reported at at least 50 N without loosening; the individual pull-test sample count was not supplied, so this result is not described as a pull test on every gland. The lid used four wing screws, allowing manual opening without a tool. This is an access feature, not permission to open energized equipment.
The owner clarified that no formal IP54 type test was performed. Instead, the project used a field sealing check with the openings plugged, low-pressure air introduced through a gland, and external joints observed with soap solution. The recorded pressure was 10 kPa gauge, held for 5 minutes, with a pressure-loss limit of 0.5 kPa and no continuous bubbles at the observed seals. These are the project’s recorded conditions, not a procedure or pressure recommendation for other enclosures. Pressure testing requires a suitable controlled setup and risk assessment; see HSE pressure-testing guidance.
Coverage was one factory first article and three arrival samples. The other 33 arrival units received appearance, gasket-contact and light-gap checks rather than the timed pressure check. After installation, all 36 assemblies received visual light-gap checks around their joints, lids and glands. The arrival sample may include a previously checked unit; the record does not assert four different units or 36 pressure-tested boxes.
The pressure and contact observations supported the project’s field acceptance. They are not a dust-chamber or water-ingress test, and this case does not assign an IP54 rating. Keeping those two statements separate prevents a useful assembly check from becoming an unsupported certification claim.
Finish checks and recorded corrections
Measured powder-coat thickness was 60–85 μm. Inspection reported no runs or exposed substrate in the checked finish, no cracking at the bends and no prominent weld marks after dressing. One box subsequently had a localized transport paint chip of less than 0.8 cm², which was repaired with a matching-color touch-up. No separate corrosion-life result is claimed for that repair.
Two spare-opening plugs were initially too tight. Their edges were sanded for acceptable assembly, and a 0.2 mm change to the plug outside-diameter tolerance was fed back for subsequent production. The record does not turn that instruction into an already verified later-batch improvement.
A further issue concerns the grounding screw position relative to certain motor cable-exit directions. The current installation could be arranged by changing the wiring direction, but reviewing the grounding-stud location remains an open design action. The gland-orientation guide addresses this interaction between hardware access, cable routing and surrounding motor geometry.
Project results and repeat-order controls
| Item | Recorded result | Coverage or next action |
|---|---|---|
| Mounting geometry | Hole position ≤0.12 mm; seating flatness ≤0.08 mm | One full first article and six production dimensional/fit samples |
| Entry threads | PG13.5 go/no-go checks passed | Reported full entry-thread inspection |
| Field sealing | 10 kPa gauge for 5 min; loss ≤0.5 kPa | One factory first article and three arrival samples, not an IP54 test |
| Installed seal contact | No visible light gaps | All 36 installed assemblies |
| Finish and plugs | 60–85 μm coating; two tight plugs and one paint chip corrected | Plug tolerance change recorded for the next batch |
| Grounding access | Current cable direction adjusted | Stud-position design review remains open |
For comparable custom motor terminal boxes, the most useful RFQ combines the motor-seat drawing, terminal-board layout, selected glands, cable directions and finished gasket interface. This project demonstrates why the inspection plan should name the feature, assembly state and sample coverage together: a mating-face result, a thread-gauge result and a field seal check are three different pieces of evidence.