This dry-transformer enclosure project supplied 12 metalwork sets for a 10 kVA equipment application. The cabinet had to match the transformer base, provide a usable front service opening and retain controlled panel fit after coating. The delivered scope was the fabricated enclosure and its mechanical accessories, not a newly certified transformer or a general electrical-performance rating.
The most useful project findings were at the interfaces: initial base slots did not provide enough adjustment, three units needed additional cleaning behind the louvers, and the common-key locks did not provide zoned access control. The first two matters were corrected on the delivered batch; the lock configuration remained as supplied, with a possible future upgrade identified.
One front door and a fixed rear panel
Each enclosure had one front service door. The rear was a fixed panel, not another access door. Keeping this configuration explicit avoids an incorrect interpretation of the door-fit results or of the space required for maintenance. The delivered package contained 12 main bodies, 12 front doors and 24 adjustable base-bracket sets, with locks and grounding terminals.
The material was SPCC cold-rolled steel. Side panels and reinforced doors were 1.5 mm, the top was 2.0 mm, and the supporting feet were 3.0 mm. Both sides received RAL 7035 powder coating; the floor-contact areas of the feet had additional anti-rust primer. Ventilation-louver edges were deburred.
The enclosure was configured for front service access. Its installation arrangement is specific to the customer’s equipment and is not used here as a generic ventilation-clearance recommendation. The transformer enclosure supply-scope guide explains which metalwork interfaces should be defined by the equipment OEM before fabrication.
Inspection coverage and base fit
One first article received full-dimensional inspection and complete assembly verification. Three production units received key mounting-dimension and door-fit checks. The remaining units received appearance and accessory-completeness checks. This is not a claim that every enclosure had a full CMM inspection or every subsequent functional test.
The checked transformer-base interfaces fitted the intended mounting pattern, with recorded hole-position deviation ≤0.2 mm. Cabinet verticality was recorded at ≤1.0 mm/m. The checked feet supported the assembly without reported rocking. These results apply to this enclosure and mounting arrangement, not to an unrestricted transformer mass or lifting load.
The first assembly exposed a practical shortcoming: the base mounting slots were 2 mm too short to provide the desired adjustment. The current batch was enlarged on site and accepted. A 5 mm slot-length increase was instructed for subsequent production. The current rework and the future drawing change are separate actions; no later-batch inspection result is implied.
The base-mounting datum guide covers this same distinction between a nominal hole location and the usable adjustment envelope after the transformer, washer and fastening stack are present.
Door fit, locks and panel stiffness
The front door closed with recorded perimeter gaps of 0.3–0.6 mm, and step mismatch was ≤0.2 mm. The lock operated smoothly and aligned with its receiving feature. The continuous gasket showed no reported breaks at the checked contact interfaces. These results concern the single front door, not front and rear doors.
A project top-panel check used a 50 kg uniformly distributed load. The reported deflection was ≤1.5 mm, with no reported permanent set after unloading. The supplied record does not specify a test duration or individual unit count for this check, so it is not presented as a 12-unit proof test, a lifting qualification or a safe standing surface. Any different load arrangement requires its own review.
The front-access design also needs a controlled removal and tool path, not just a door that closes at the factory. The service-panel access guide helps buyers identify which clearances belong on the equipment layout and which belong on the enclosure drawing.
Field observations without an unsupported IP rating
The owner confirmed that no formal IP4X probe test was performed. Field gap measurements were made on all 12 enclosures, with a reported maximum gap of 0.8 mm in the checked locations. Separately, two units were observed after 72 hours of unloaded on-site operation. The owner reported no obvious accumulated dust, with only small amounts of naturally settled dust visible.
Those are field inspection and observation records. A measured gap is not, by itself, an IP4X test result; nor does IP4X describe dust-tight performance. This case therefore does not claim an IP4X rating or a passed dust test. The observations also do not establish transformer temperature rise, insulation life or the suitability of a different operating environment.
The louver openings followed the project’s design. Their existence and recorded edge condition do not substitute for the equipment designer’s airflow and thermal checks. Keeping the thermal requirement with the OEM allows the fabricator to quote and inspect the actual panel geometry without inventing performance from sheet-metal appearance.
Finish, cleaning and follow-up actions
Measured exterior coating thickness was 70–90 μm; the interior was 50–70 μm. The finish checks reported no obvious color inconsistency or impact damage, and the reinforced door and dressed metalwork were acceptable in the checked condition. These are coating and visual records, not a corrosion-duration result.
Three enclosures retained small amounts of punching oil on the inside of the louvers. The residue was removed on site, and production was asked to add a degreasing step. That correction is useful because a finished exterior alone would not have exposed the hidden cleaning issue.
The supplied locks used common keys. Where separate access zones are needed, a different lock arrangement remains an option, but it was not installed as part of this delivery. The case does not describe the current cabinet as having controlled or individually keyed security.
| Interface | Recorded result | Scope or follow-up |
|---|---|---|
| Base mounting | Position deviation ≤0.2 mm; checked interfaces fitted | One first article and three production samples |
| Front door | Gap 0.3–0.6 mm; step ≤0.2 mm | Single front door; fixed rear panel |
| Top panel | 50 kg distributed check; deflection ≤1.5 mm | Reported project check, not a general load rating |
| Field gaps | Maximum recorded gap 0.8 mm | 12 units; no formal IP4X probe test |
| Operating observation | No obvious dust accumulation after 72 unloaded hours | Two units; not thermal or insulation qualification |
| Rework | Slots enlarged; three oily louver areas cleaned | Future slot-length and degreasing changes recorded |
For custom transformer enclosures, a useful repeat-order package carries forward the corrected slot geometry, front-door configuration, mounting hardware and interior cleaning requirement. It should also identify the exact transformer variant and OEM ventilation drawing. This project shows why base adjustment, service access and hidden-surface inspection belong in the same manufacturing review.