Engineering resources / Order collaboration

For purchasing, engineering and supplier quality

Working with DRAmetal

From an accepted quotation to a controlled repeat order: know what to confirm, which records to expect and where an approval is needed before work proceeds.

Review the six order stages
Agree the project terms first. This workflow is a coordination guide. The accepted quotation, order acknowledgment, released technical package and agreed quality clauses define your deliverables, approval gates, timing and responsibilities.
One sales contact, coordinated internally

Keep order communication in one place

Your sales contact coordinates engineering, production, quality and logistics. Send order changes, receiving issues and supplier-qualification requests to sales@drametal.com, with the order or project reference and current revision.

Milestone updates

Updates cover order confirmation and advance payment, material arrival / production start, FAI results and reports, production and agreed inspection completion, and dispatch-day shipping documents where applicable. Orders of at least 500 pieces or with an agreed lead time of at least 30 days also receive an update every Friday.

Risk notification

Your sales contact reports a risk on the day it is identified, with a message and formal email explaining the cause, expected timing and actions. A confirmed delay is escalated immediately by phone or video and email. Drawing or payment delays are addressed by email that day to confirm rescheduling.

Planning ranges, confirmed for your order

Typical lead times and commercial scope

These typical production ranges include cutting, bending, welding and standard surface treatment, including outsourced powder coating or zinc plating. They are not unconditional delivery promises: the quotation and order acknowledgment confirm the applicable scope, capacity, approval gates and shipment arrangement.

First article / prototype

7–10 working days

Starts from: Final drawing approval and receipt of advance payment.

Production: 100–500 pieces

15–20 working days

Starts from: Final drawing approval and receipt of advance payment; depends on complexity.

Production: more than 500 pieces

25–35 working days

Starts from: Final drawing approval and receipt of advance payment; production scheduling is required.

Unchanged repeat order

10–15 working days

Starts from: Confirmation of unchanged drawings and the purchase order; customer first-article approval rules still apply.

Quantities, price breaks and expedited orders

Prototype MOQ is 1 piece. Quantities of 50 or more can spread setup costs across more parts; this is an economic batch reference, not a guaranteed lowest price. Ask for comparable quotation tiers at 100, 500 and 1,000 pieces using the same revision, finish and inspection scope.

Expedited production can be discussed subject to capacity confirmation. An additional charge of approximately 15–30% may apply; the scope, fee and achievable date must be agreed before release.

Included shipment documents and additional report charges
  • Standard, no additional charge: commercial invoice, packing list, mill material test certificate (MTC) and outgoing inspection report (OQC) covering routine visual checks and dimensional sampling. MTCs can be provided for SPCC, SECC and AL5052; confirm records for other specified materials at quotation.
  • First article and measurement: the full-dimensional FAI report for a first order is free. Full-dimensional reinspection for a repeat order is approximately USD 80–150 per part type. CMM reporting is agreed separately, priced by measurement points or included in the FAI scope. Customer approval requirements remain as defined in the first-article stage.
  • Coating and external tests: basic coating-thickness checks at 5–10 points are free. Adhesion, hardness and salt-spray tests are agreed separately. Third-party salt-spray testing typically requires 7–30 days, with fees dependent on test duration.
  • Supplier qualification: scanned management-system certification documents are available free at quotation stage through sales@drametal.com.

Confirm the required report format, characteristics, coverage and additional charges in the quotation. A free or paid report does not change the agreed acceptance criteria or approval authority.

Split deliveries, forecast stock and replenishment arrangements

Agree each split shipment's quantity and delivery date when confirming the purchase order. Freight is charged for each shipment. Keep part revisions, quantities and release records identifiable across the deliveries.

Forecast-based stocking requires an annual framework agreement and a stocking deposit, typically 30%. Safety stock is limited to commonly used standard items; custom parts are not routinely held in stock. Confirm ownership, replenishment, revision changes and obsolete-stock disposition before setting up a program.

Vendor-managed inventory (VMI) is not a standard service. A separate arrangement may be discussed for a strategic customer; it must not be assumed from a forecast or repeat order.

A shared release path

Six stages, with an owner for each decision

Use the order reference and current revision in each approval or change request. Confirm which checkpoints need a buyer response, how progress will be communicated and who can release the next stage.

  1. Order confirmation

    Buyer action
    Check the quoted part list, quantities, price basis, delivery terms and required records against your purchase order. Name the engineering, quality and purchasing contacts who can approve changes.
    DRAmetal coordination
    Resolve differences between the quotation and purchase order, then confirm the accepted scope, dependencies and delivery milestone in the order acknowledgment.

    Confirm before proceeding: Conflicting specifications, unaccepted commercial terms or missing approval authority need clarification before the affected work is released. A requested date is not a confirmed delivery commitment.

  2. Release the manufacturing revision

    Buyer action
    Identify the controlling drawing and model revisions, BOM, approved components, finish, critical interfaces and inspection requirements. Resolve any DFM proposal that changes the design.
    DRAmetal coordination
    Check the manufacturing package against the agreed order and record open questions. Carry the approved configuration into production instructions, purchasing and inspection planning.

    Confirm before proceeding: Unresolved drawing/model conflicts, unapproved substitutions or a pending engineering change hold the affected procurement or manufacturing operation. A discussion drawing is not a production release.

  3. First article approval and written waivers

    Buyer action
    Customer first-article approval is required for new customers, new products, orders involving a change, and any single order of 100 pieces or more. Agree the sample quantity, characteristics and report scope in writing, then return approval or a documented disposition through an authorized contact.
    DRAmetal coordination
    Provide the first-build checks and agreed records, identify deviations and verify the customer approval before batch release. Any proposed waiver of customer approval is also checked by the internal quality lead.

    Confirm before proceeding: Orders below 20 pieces and unchanged repeat orders are not automatically exempt. Skipping customer approval requires a valid existing written waiver agreement, or a written waiver from an authorized customer representative covering the part, revision and order, plus confirmation by the internal quality lead. This does not waive agreed inspection or batch acceptance requirements.

  4. Batch production

    Buyer action
    Keep the released configuration stable and communicate quantity, delivery or design changes with the order reference. Confirm the disposition of affected material, work in progress and finished stock before a change takes effect.
    DRAmetal coordination
    Coordinate the agreed fabrication, finish and assembly route with the production and inspection records required by the order. Review the effect of a requested change on cost, checks and schedule before implementation.

    Confirm before proceeding: An unresolved nonconformance, unavailable approved component or proposed substitution needs a recorded decision for the affected work. A repeat part number alone does not authorize a changed material, finish or component.

  5. Inspection and shipment release

    Buyer action
    Confirm any customer sign-off, witness inspection or report review required before shipment. Review deviations against the agreed acceptance criteria, not an informal replacement tolerance.
    DRAmetal coordination
    Complete the agreed first-article, sampled or all-unit checks and review identification, quantities and required documents. Keep inspection coverage and any authorized deviation connected to the shipment configuration.

    Confirm before proceeding: Missing required records, unresolved acceptance results or an outstanding contractual release approval hold the affected shipment. Sampled results must not be presented as inspection of every delivered unit.

  6. Shipping and receiving

    Buyer action
    Confirm the consignee, delivery address, receiving constraints and any nominated carrier. At receipt, compare package identification, quantities and documents with the order; record damage or discrepancies before mixing affected items with accepted stock.
    DRAmetal coordination
    Arrange the packaging, identification, shipment documents and transport responsibilities accepted in the quotation or order acknowledgment. Share the agreed handover information for the shipment.

    Confirm before proceeding: Unconfirmed shipping instructions, unresolved packout requirements or missing release documents require clarification before dispatch. Freight responsibility and risk transfer follow the agreed Incoterm and contract, not the factory completion date alone.

Inspection release is not the whole handover

Agree how the receiving team will identify the shipment

Build the packout requirement around the part, finish, destination and receiving process. The standard document package and optional reports are listed above; labels, photos and special packaging follow the agreed order scope.

Identity and quantity

Agree the order/line reference, part and revision identification, kit or assembly number, package count, quantity per package and lot reference where required. Keep mixed revisions and accepted deviations identifiable.

Protection and handling

Specify vulnerable surfaces, machined interfaces, threads and protruding hardware. Agree separators, restraint, corrosion protection, reusable packaging or lifting instructions when the project requires them.

Documents and release

Identify the packing list, inspection records, material records, approved deviations and shipping documents that must accompany the order. Agree whether any customer document review is required before dispatch.

Galvanized sheet metal brackets separated by soft padding in corrugated carton dividers
Packaging method — surface separation. Soft interleaves and carton dividers keep adjacent formed parts apart. Select cushioning and restraint for the part geometry and transport conditions.
If an issue is found

Keep the affected items and evidence identifiable

Report the order reference, part/revision, quantity affected, package or lot identification and the observed problem to your sales contact at sales@drametal.com. Include relevant photos, the requirement and measurement method when a dimensional issue is involved.

Separate affected items from accepted stock. Agree containment, review and disposition before rework, use, return or disposal; preserve the original condition where practical so the issue can be investigated.

After the first shipment

Release the next order against a known configuration

A previous accepted batch is a useful reference, not automatic authorization to reuse every condition. Confirm the current revision, quantity, approved sourcing, inspection scope and delivery arrangement for the next release. Inventory, reserved capacity and tooling arrangements require separate agreement where applicable.